Construction to Begin in Mid-September 2007
National Fuel Gas Company's ("National Fuel" or "Company") (NYSE:
NFG) wholly owned subsidiary, Empire State Pipeline ("Empire"), has
reached major milestones and is on schedule for its pipeline expansion
project, the Empire Connector, to be completed and in service in the
fall of 2008. Recent project developments include: the execution of a
service agreement with a KeySpan Energy Corp. company for more than
60% of the pipeline's capacity; contracting for the pipeline and
compressor station equipment; engaging Otis Eastern Service,
Incorporated as its pipeline construction contractor; and finalizing
the project's construction schedule, with approximately 20 to 25 miles
of pipeline construction slated for this year.
"We are pleased to see the next phases of this project coming to
fruition," said David F. Smith, President and Chief Operating Officer
of National Fuel Gas Company and President of Empire State Pipeline.
"For more than four years, we have worked diligently with landowners,
representatives from environmental agencies, agricultural specialists
and legislators to move this project forward. Reaching this juncture
would not have been possible without the cooperation of those affected
by this important project, particularly the landowners along the
pipeline route, who helped us develop a solid plan for this project.
We are grateful for their input and look forward to the value this new
infrastructure will bring to both New York State and National Fuel.*"
The Empire Connector Project will expand the 157-mile long Empire
State Pipeline by about 77 miles. Project costs are estimated to be
approximately $177 million. Extending from Victor, N.Y., to Corning,
N.Y., the Empire Connector will link the existing Empire State
Pipeline that runs from near Buffalo, N.Y., to Syracuse, N.Y., to the
Millennium Pipeline project. One compressor station will be built as
part of the Empire Connector Project. The compressor station will be
located in Oakfield, N.Y., and will increase the pipeline's ability to
deliver gas along the expanded pipeline system. The Empire Connector
and the Millennium Pipelines are part of a significant expansion
project designed to bring much-needed energy supplies to the
Northeast. Once completed, these projects, along with the Algonquin
Gas Transmission, LLC and Iroquois Gas Transmission System, L.P.
expansion projects, will provide 525,400 dekatherms per day (dth/d) of
new natural gas supply to growing markets in the Northeast.* When
these pipeline projects are completed, natural gas will flow from
increasingly important and substantial North American supply basins to
markets in the Northeast - serving customers in central and western
New York along the way.*
Earlier this summer, a subsidiary of KeySpan Energy Corp. (NYSE:
KSE), the largest distributor of natural gas in the Northeast,
executed its firm transportation service agreement with Empire,
providing for at least ten years of 150,750 dth/d of natural gas
transportation service on the Empire State Pipeline, including the
Empire Connector facilities.* KeySpan, which serves more than 2.5
million gas customers in the Northeast, is also New York's largest
investor-owned electric generator and operates the Long Island Power
Authority electric system serving 1.1 million customers. Empire is now
actively marketing the remaining capacity that will be created by the
Empire Connector.
"We are literally at the stage where all of the pieces to this
project are coming together. Securing the materials and resources
needed to construct energy infrastructure at a time in our industry
when such things are at a premium is a significant milestone to reach.
Right now, the pipe we'll use is being manufactured in Baton Rouge,
Louisiana and the compressor equipment is being manufactured in San
Diego, California," said Ronald C. Kraemer, Vice President, Empire
State Pipeline. These components alone represent more than $30 million
of the total project cost.
In another significant project development, Empire has engaged
Wellsville, N.Y.,-based Otis Eastern Service, Incorporated as the
construction contractor for the pipeline project. "We are pleased to
be working with a local pipeline contractor with the capability and
reputation to schedule and manage projects in a safe and timely
manner. Otis Eastern has demonstrated experience in successfully
completing pipeline construction projects throughout New York State,
through all types of terrain, including agricultural lands, and in
doing so with the utmost respect for the local natural resources" said
Kraemer.
Representatives from Empire will continue to work directly with
landowners and affected parties along the pipeline route at the
beginning of, and throughout, the construction process. The first
phase of pipeline construction is scheduled to begin in mid-September
in Yates and Schuyler Counties, with 20 to 25 miles of construction
being planned for completion by early December. The rest of the
pipeline route, including the compressor station, will be constructed
in 2008. Those who own property in the area identified for
construction this year will be contacted by a representative from
Empire and will have an opportunity to meet with the project team in
advance of the start of construction.
National Fuel Gas Company is an integrated energy company with
$3.8 billion in assets comprised of the following five operating
segments: Utility, Pipeline and Storage, Exploration and Production,
Energy Marketing, and Timber. Additional information about National
Fuel Gas Company is available on its Internet Web site:
www.nationalfuelgas.com or through its investor information service at
1-800-334-2188. For more information about the Empire Connector, visit
the project's Web site at www.empireconnector.com.
* - Certain statements contained herein, including statements
concerning plans, objectives, goals, projections, strategies and
future events or performance, statements which are designated with an
asterisk ("*"), and statements which are identified by use of the
words "anticipates," "estimates," "expects," "intends," "plans,"
"predicts," "projects," and similar expressions, are "forward-looking
statements" as defined by the Private Securities Litigation Reform Act
of 1995. Forward-looking statements involve risks and uncertainties
which could cause actual results or outcomes to differ materially from
those expressed in such statements. The Company's expectations,
beliefs and projections contained herein are expressed in good faith
and are believed to have a reasonable basis, but there can be no
assurance that such expectations, beliefs or projections will result
or be achieved or accomplished. In addition to other factors, the
following are important factors that could cause actual results to
differ materially from those discussed in the forward-looking
statements: changes in economic conditions, including economic
disruptions caused by terrorist activities, acts of war or major
accidents; changes in demographic patterns or weather conditions,
including the occurrence of severe weather; changes in the
availability and/or price of natural gas, oil and coal; inability to
obtain or retain sufficient customers for the proposed Empire
Connector; changes in the plans of the sponsors of the proposed
Millennium Pipeline with respect to that project; significant changes
in competitive factors affecting the Company; governmental/regulatory
actions, initiatives and proceedings, including the FERC's
consideration of the proposed Empire Connector, and other federal,
state or local actions, initiatives or proceedings affecting
acquisitions, financings, allowed rates of return, affiliate
relationships, industry and rate structure, franchise renewal, and
environmental/safety requirements; unanticipated impacts of
restructuring initiatives in the natural gas and electric industries;
significant changes from expectations in actual capital expenditures
and operating expenses and unanticipated project delays or changes in
project costs; significant changes in the projected profitability of
pending and potential projects, including the proposed Empire
Connector; occurrences affecting the Company's ability to obtain funds
from operations or the issuance of debt or equity securities to
finance needed capital expenditures and other investments; significant
changes in the Company's relationship with its employees and
contractors and the potential adverse effects if labor disputes,
grievances or shortages were to occur; changes in laws and regulations
to which the Company is subject, including tax, environmental, safety
and employment laws and regulations; or the cost and effects of legal
and administrative claims against the Company. The Company disclaims
any obligation to update any forward-looking statements to reflect
events or circumstances after the date hereof or to reflect the
occurrence of unanticipated events.
CONTACT:
National Fuel Gas Company
Media:
Julie C. Cox, 716-857-7079
Analyst:
James M. Welch, 716-857-6987