WILLIAMVILLE, N.Y.--(BUSINESS WIRE)--July 14, 2006--National Fuel
Gas Company ("National Fuel" or "Company") (NYSE: NFG) today announced
that its wholly owned subsidiary, Empire State Pipeline ("Empire"),
has revised the planned in-service date for the proposed Empire
Connector natural gas pipeline to extend beyond November 1, 2007.
Empire has aligned this project with the timing of other, related,
pipeline expansion projects, all of which are now anticipating an
in-service date beyond November 1, 2007 to November 1, 2008, or sooner
if feasible.
In a letter recently submitted to the Federal Energy Regulatory
Commission ("FERC"), Empire, along with project sponsors of the
related pipeline expansion projects, emphasized their request that the
FERC issue their respective authorizations no later than November 1,
2006, given the applicants' need to secure multiple permits for
construction, acquire line-pipe, compressors, related equipment and
contractor construction services, and complete the requisite
pre-construction activities.
"We successfully launched this important project in 2004 and it is
making excellent progress, thanks primarily to the cooperation and
assistance received from landowners along the proposed Empire
Connector route and various permitting agencies," said Ronald Kraemer,
Vice President of the Empire State Pipeline. "We will continue to work
with landowners and stakeholders along the route as we move ahead with
this project."* Construction of the pipeline could start as soon as
late summer 2007 in an attempt to minimize impacts in certain areas of
the pipeline route.*
National Fuel owns and operates the Empire State Pipeline, an
existing 24-inch diameter natural gas transmission pipeline that
originates at the United States-Canada border at the Chippawa Channel
of the Niagara River and extends easterly 157 miles from Buffalo, N.Y.
to near Syracuse, N.Y.
Developing the Empire Connector project involves constructing a
pipeline southward from this existing line near Rochester, N.Y. to
connect with the Millennium Pipeline near Corning, N.Y.* Empire will
construct approximately 78 miles of 24-inch diameter pipeline and one
compressor station that will produce 20,620 horsepower.*
The pipeline extension will be designed to move 250 million cubic
feet (MMcf) of natural gas per day into the Millennium Pipeline and
may provide customers on Empire with access to a number of underground
storage facilities and local distribution companies' pipeline systems
in New York state.* Empire's customers will also have access to
abundant and diverse gas supplies at the Dawn hub through Empire's
connection with the TransCanada PipeLine system at Chippawa.* The $144
million project is designed to help New York and the Northeast meet
their increasing demand for energy.
"The energy industry and its customers continue to struggle with
the negative consequences associated with imbalances in the
marketplace that brings energy to consumers in the Northeast. Events
last year and sustained high energy prices demonstrate the need for
new pipeline capacity to diversify the options available for moving
new gas supply to where it's consumed," Kraemer added.
KeySpan Energy Corp. (NYSE: KSE), the largest distributor of
natural gas in the Northeast, has subscribed for 150 MMcf of natural
gas transportation service per day on the Empire and Millennium
Pipeline systems.* KeySpan, which serves more than 2.5 million gas
customers in the Northeast, is also New York's largest investor-owned
electric generator and operates the Long Island Power Authority
electric system serving 1.1 million customers.
National Fuel is an integrated energy company with $3.9 billion in
assets comprising the following five operating segments: Utility,
Pipeline and Storage, Exploration and Production, Energy Marketing,
and Timber. Additional information about National Fuel is available on
its Web site, www.nationalfuelgas.com, or through its investor
information service at 1-800-334-2188. For more information about the
Empire Connector, visit the project's website at
www.empireconnector.com.
Certain statements contained herein, including statements
concerning plans, objectives, goals, projections, strategies and
future events or performance, and statements which are designated with
an asterisk ("*"), are "forward-looking statements" as defined by the
Private Securities Litigation Reform Act of 1995 and involve risks and
uncertainties which could cause actual results or outcomes to differ
materially from those expressed in the forward-looking statements. The
Company's expectations, beliefs and projections contained herein are
expressed in good faith and are believed to have a reasonable basis,
but there can be no assurance that such expectations, beliefs or
projections will result or be achieved or accomplished. In addition to
other factors, the following are important factors that could cause
actual results to differ materially from those discussed in the
forward-looking statements: changes in economic conditions, including
economic disruptions caused by terrorist activities, acts of war or
major accidents; changes in demographic patterns and weather
conditions, including the occurrence of severe weather, such as
hurricanes; changes in the availability and/or price of natural gas,
oil and coal; inability to obtain new customers or retain existing
ones; significant changes in competitive factors affecting the
Company; governmental/regulatory actions, initiatives and proceedings,
including those involving the Empire Connector project, acquisitions,
financings, rate cases (which address, among other things, allowed
rates of return, rate design and retained gas), affiliate
relationships, industry structure, franchise renewal, and
environmental/safety requirements; unanticipated impacts of
restructuring initiatives in the natural gas and electric industries;
significant changes from expectations in actual capital expenditures
and operating expenses, and unanticipated project delays or changes in
project costs or plans, including changes in the plans of the sponsors
of the proposed Millennium Pipeline with respect to that project; the
nature and projected profitability of pending and potential projects
and other investments; occurrences affecting the Company's ability to
obtain funds from operations, debt or equity to finance needed capital
expenditures and other investments, including any downgrades in the
Company's credit ratings; changes in the availability and/or price of
derivative financial instruments; changes in the price of natural gas
or oil; significant changes in tax rates or policies or in rates of
inflation or interest; significant changes in the Company's
relationship with its employees and contractors and the potential
adverse effects if labor disputes, grievances or shortages were to
occur; changes in laws and regulations to which the Company is
subject, including tax, environmental, safety and employment laws and
regulations; or the cost and effects of legal and administrative
claims against the Company. The Company disclaims any obligation to
update any forward-looking statements to reflect events or
circumstances after the date hereof or to reflect the occurrence of
unanticipated events.